Realisation

Key words:

2009 - Neilson-EBC
Waskaganish
Foundations of Waskaganish's drinking water treatment plant
The particularity of this project, whick required approximately 1200m3 of concrete, is the fact that it had to be perfectly tight due to the vocation of the building. The concrete is thus perfect, completely free of cracks.

 

2008 - Wabannutao Eeyou Development Corporation
Eastmain
Clearing of right of way of Eleonore 69 kV line
So far, 2.2 km of fascine and 52 km of road with several of them made in a rock field were done in this project.

2008 - Hydro-Québec
DynamitingKuujjuaq
Construction of the new access road and foundations for Kuujjuaq's new power house
All the works of dynamiting and excavation, as well as all the civil works required by the concrete foundations and walls of the new power house.

2008 - Laval Fortin Adams
Kuujjuaq
Reconstruction of the worker's accomodations
Nearly one million dollars was invested in Kuujjuaq LFA camp retrofit.

2008 - Société d'énergie de la Baie-James
Eastmain
Collection and elimination of the ligneous debris
These works consisted in the collection and the burning of the ligneous debris accumulated in Eastmain EM-1-A reservoir in James Bay region. We had to clean approximately 20 km of beach on a width from 1 to 10 metres.  

2008 - First Air Ltd.
Iqaluit
Airplane hangar renovation
The project consists in the installation of a megadome, the renovation of a temporary administration building, and almost the reconstruction of the existing hangar.    

2007 - Public Works and Government Services Canada
Iqaluit
Construction of the Royal Canadian Mounted Police headquarters of Iqaluit
All the civil work that will lead to the complete erection of this building, including 2 floors: offices and a carceral part. This project is phase 1 of a bigger project including lodging for officers.

2007 - Public Works and Government Services Canada
Wemindji airport terminalWemindji
Setting of standards of the Wemindji airport
This project consisted in different kinds of works leading to the setting of standards of the Wemindji airport.

2007 - Kativik School Board
The administrative buildingKuujjuaq
Administrative building

The works of dynamiting, concreting and all other works concerning the erection of an 860m2 building, intended to welcome the administrative offices of the Kativik School Board, in Kuujjuaq.

2007 - The Perseverance mine project
Matagami Perseverance mine siteMatagami
Laval Fortin Adams
Our company can be proud to have contributed to this wide-ranging project by building in part or in whole several infrastructures surrounding the Matagami Perseverance mine.